The new factory
Our company's new plant is located in Lipu, Guilin City, Guangxi Province; the designed capacity is 120K m2/month, and the overall plant area is 15000m2.
it was started construction in May 2022. As of today:
All the large-scale equipment has arrived at the factory: 100k capacity PTH prouction line, two 60k capacity electroplating gantry lines, dry area pretreatment horizontal line, tunnel oven, automatic LED exposure machine, LDI exposure machine.
Supporting facilities on the roof: water, electricity and gas projects are also in the process of installation and commissioning. The renovation of the office area on the first floor is nearing completion. Preliminary trial operation is scheduled in the late September, and the opening ceremony will be held on October 10.